Freeway Performance Initiative - TOS and Ramp Meter

Description: At various locations in Alameda, Santa Clara, and Solano Counties. Install ramp metering and traffic operations system elements along various routes.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda, Solano
City
Zip Code
 
Senate District
04, 14, 16, 18, 20, 24, 25, 27, 28
Assembly District 07, 09, 10, 13, 15
Congressional District 03, 05, 13, 15, 17, 18, 19
 
Caltrans District
04
 
 
County/State Route Alameda 80
Postmile Begin/End 0 28.4
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  4000    4000  
Peak Period Time Savings (minutes)  59000    59000  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Val Ignacio (510)286-5086   Val_Ignacio@dot.ca.gov
Design (PS&E) Phase
Caltrans Val Ignacio (510)286-5086   Val_Ignacio@dot.ca.gov
Right of Way Phase
Caltrans Val Ignacio (510)286-5086   Val_Ignacio@dot.ca.gov
Construction Phase
Caltrans Val Ignacio (510)286-5086   Val_Ignacio@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$42,957 $-6,900 $36,057
Non-bond Funding
State/Federal*
$27,000 $-5,121 $21,879
Local**
$14,782 $2,266 $17,048
Non Budgeted ETC
$0 $0 $0
 
Total**** $84,739 $-9,755 $74,984

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$4,954 $2,336 $7,290 $5,999
Design(PS&E)
$8,755 $-1,751 $7,004 $8,395
Right of Way
$1,073 $0 $1,073 $305
Construction
$69,957 $-10,340 $59,617 $56,462
 
Total* $84,739 $-9,755 $74,984 $71,161

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
08/01/2010 

07/01/2011 
 

 
08/01/2010 

07/01/2011 
100  09/01/2009 

08/01/2011 
11 

-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/01/2010 

05/01/2012 
 

 
08/01/2010 

05/01/2012 
100  02/01/2011 

05/01/2012 
-6 

Begin Right of Way Phase

End Right of Way Phase
08/01/2010 

05/01/2012 
 

 
08/01/2010 

05/01/2012 
100  10/01/2011 

03/26/2012 
-14 

Begin Construction Phase

End Construction Phase
09/01/2012 

10/01/2014 
 

 
09/01/2012 

10/01/2014 
10/24/2012 

09/17/2014 
-2 

Begin Closeout Phase

End Closeout Phase
10/01/2014 

04/01/2016 
 

 
10/01/2014 

04/01/2016 
100  09/18/2014 

01/02/2019 


-34 
Corridor System Management Plan
Adoption Date 12/01/2009    12/01/2009   
Implementation Date 12/01/2009    12/01/2009   
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 4000 4000
Peak Period Time Savings (minutes) 59000 59000

Bond Funding Cost
Adopted:
$42,957,000
Current Approved:
$36,057,000
Actual Expenditures:
$35,928,000

 

Status as of December 31, 2023.